Ace Quantum Chemical Tankers CV v Nordic Tankers Trading. (MN “Chem Sirius”) – SMA No.4392, 26 July 2020
SPOT CHARTER – PRORATED WAITING TIME – SUSPENDED LAYTIME – DROPPED TENDER
Vessel tendered NOR whilst charterer’s berth was available and after awaiting a short period of time, went to another berth. Thereafter, charterer’s berth was occupied and vessel periodically waited for charterer’s berth and worked berths for other charterers’ accounts. Owner claimed as demurrage those periods of time whilst vessel was awaiting charterer’s berth whilst it was charterer’s position that the root cause of the overall delay in berthing was vessel’s decision to not work charterer’s berth when given the opportunity.