London Arbitration 11/22

TIME TRIP CHARTERPARTY – AMENDED NYPE 93– LEGAL FEES – DEVIATION CLAUSE – BUNKERS – CREW CHANGE – WEATHER DELAY
A vessel was chartered for a 25-30 day period to load at a port in the Sea of Japan and discharge at a port in the South China Sea. The parties agreed the vessel would deviate to Hongai, Vietnam for a crew change. After leaving Hongai, the vessel encountered bad weather, resulting in a 1.05 day delay. The charterer claimed the weather delay would not have occurred if the vessel had made a direct journey. The owner claimed the vessel was on hire at the time of the weather delay.