NYPE -- LATE REDELIVERY -- WHETHER SUBSEQUENT LOST PROFITS WERE FORSEEABLE -- DAMAGES UNDER SUBSEQUENT FIXTURE -- Charterer Award
Following the late redelivery of the Vessel from a time charter, Owners were forced to renegotiate their next time charter at a lower rate. Owners claimed $1.3 million in damages and won the dispute. On this appeal by Charterers, the Panel overturned the previous ruling with the simple question "Would an objective person have anticipated such a large loss of profits from the redelivery of a time chartered vessel made nine days late?" The award details the Panel's ruling and settlement.
SHELLTIME 4 -- VESSEL FITNESS FOR SERVICE WHEN REGULATIONS RESTRICTING CARGOES CHANGE -- MARPOL -- SEAWORTHINESS -- Charterer Award
Two vessels were contracted for the carriage of fuel oils, but following the fixture, MARPOL regulations were changed, requiring fuel oil to be carried only in double-hulled ships. The Court of Appeal upheld the High Court's decision, and described what changes could have been made to the two vessels to bring them in compliance with the new MARPOL regulations.
ASBATANKVOY -- RESPONSIBILITY FOR "PIER DUES" -- CONFLICTING CLAUSES -- AMENDMENTS -- Charterer Award
Although this award focuses on the responsibility for paying pier dues, it is relevant to laytime and demurrage in that the charter party contains two clauses which are in conflict. The Panel determines which clause takes precedence, and explains why.
STEMMOR -- ACCEPTANCE OF NOR -- REVERSIBLE LAYTIME -- TIME COUNTING DURING BUNKERING -- Owner Award
The Panel is asked to rule on a variety of topics, including whether or not the failure to reject a NOR means that it is inherently accepted, the nature of "reversible" laytime and how laytime should be calculated for separate parcels, and whether time spent bunkering while waiting for an available berth counts as laytime.
In London Arbitration 8/08 we saw the tribunal rule that time during which a vessel bunkers at a waiting anchorage (i.e. charterers’ berth is not available) is to count as laytime or as time on demurrage. In making their ruling, the panel concluded that no time was lost as the vessel would not have been able to attend to the berth even had she not been bunkering nor was the ship’s readiness deemed impaired as she was doing what the charterer had ordered her to do; wait at the anchorage.
ASBATANKVOY -- TIME-BAR -- CHARTERPARTY CONSTRUCTION -- HEATING AND PURGING -- Owner Award
Owners submitted a claim for additional heating and purging costs beyond the scope of the requirements in the charter party, but Charterers rejected the claim as time-barred. The Panel was called on to settle the dispute and explained how specific modifications to the charter party terms affected their ruling.
ASBATANKVOY -- INTERPRETATION OF RELOAD CLAUSE -- FREIGHT ASSESSMENT -- NUMBER OF CARGO GRADES CARRIED -- Charterer Award
During the discharge at Freeport, Charterers informed Owners that they planned on loading additional cargo after discharge operations completed. Owners commenced arbitration to recover this freight payment from Charterers. Charterers disagreed, claiming that they were within their rights to reload cargo at any discharge port within the scope of the charter party. This award describes how the Panel interpreted the special provisions clauses and applied them to the dispute.
GENCON -- DEMURRAGE -- WHETHER BERTH OR PORT CHARTER -- NIGHT TRANSIT -- GROUNDING -- AWAITING PILOT -- SHIFT TO BERTH -- Owner Award
This award covered a number of issues, including whether the fixture of "one safe berth" and a WIBON (whether in berth or not) constituted a berth charter party, whether or not port restrictions on night transits are demurrage events, and how a pilot shortage affected the Panel's ruling on waiting time and a grounding incident.
NYPE -- TIME CHARTER TRIP -- SUBSTANTIAL DELAYS AT DISPORT -- IMPLIED TERM TO DISCHARGE WITHIN REASONABLE TIME -- OWNERS’ CLAIM FOR FINANCIAL LOSS -- Charterer Award
Under a NYPE form time charter, the Vessel delivered cargo to Lagos, but wasn't given berthing instructions for nine months. Owners commenced arbitration to recover lost profits from the delay in redelivering the Vessel. How did the Panel define "reasonable time" under a NYPE charter party? This Panel's ruling lays out what happens when parties don't include protective clauses with specific wording in their contracts.
VEGOILVOY -- SUBSTANTIAL FAILURE OF EPOXY COATING OF CARGO TANKS -- TANK LINING -- VESSEL SUITABILITY -- WHETHER OWNERS IN BREACH OF CHARTER -- Charterer Award
The Charterer's inspector rejected the Vessel's tanks due to severe corrosion and rust, and declared the Vessel unsuitable. Charterer held the Owner in breach of the charter not only for the condition of the tanks, but also if the Vessel's tanks were actually epoxy coated as presented in the charter party. Charterer won the initial dispute in the Court of Singapore. Owners appealed, and this award details how the Court approached the issue.