BALTIME 1939 -- MASTER OVERWRITING FIGURES ON DEPARTURE DOCUMENTS -- DEPARTURE DELAY WHILE AGENT PREPARES NEW DOCUMENTS -- OFF-HIRE -- Charterer Award
Upon completion of loading Master first refused to sign required departure documents before striking through figures and writing in what he considered to be the correct amounts. There was subsequently a 24-hour delay whilst new documents were prepared which the Master signed as presented with his disagreements noted on the bottom. Against Owner’s wishes, Charterer subsequently deducted the 24-hour period from money owed for bunkers.