BALTIMORE FORM C -- MOORING PERSONNEL STRIKE -- PILOT DELAY -- WIBON CLAUSE -- NOTICE OF READINESS VALIDITY -- SUBSTANTIAL READINESS -- Charterer Award
The Vessel experienced serious delays en route to the upriver loadberth due to a strike of mooring personnel. Charterer rejected the subsequent demurrage claim, and at arbitration, they argued that (1) Shortened Proceedings should govern, (2) the loadport Notice of Readiness (NOR) was invalid because the Owner had not met all NOR requirements, and (3) the delay due to a workmen strike (mooring personnel) is exempted by a special exceptions clause.